Major Milestones | Approximate Timeline |
Developer consults with staff | Pre-submission
|
Developer coordinates good neighbor mailing | Start of process |
Developer and staff hold good neighbor meeting | Week 2 |
Developer submits materials to city | Week 2-3 |
Staff reviews materials and meets informally | Week 3-4 |
Staff prepares and mails preliminary report to developer | Week 3-4 |
Developer submits corrected/modified materials | Week 6 |
Staff reviews corrected materials, and prepares report for Planning Commission | Week 6 |
Planning Commission meets and makes recommendation to City Council | Week 7-8 |
City Council meets, holds public hearing, and may approve 1st required reading | Week 8-10
|
City Council meets and approves 2nd reading | Week 10-12 |
City Council meets and approves 3rd reading | Week 12-14 |
City publishes rezoning and the process is final | Week 13-15 |