Category: Project Updates

Eastside Utilities Project update for April 3, 2015

Weekly Overview: March 30 to April 3 Progress Meeting 1 was held and minutes distributed. FOX attended the project open house on March 31. Additional silt fence was placed to control erosion control. Discussions about stabilization required for the stream channel realignments. Langman started laying the 30-inch sanitary sewer pipe. They made the connection to…

Read More

Crews consider turtles before next steps

Last week, ahead of a March 31 deadline, clearing was completed for the first step of North Liberty’s utilities expansion to serve Liberty High School and the surrounding area. Soon, crews will begin installing pipe from the waste water treatment plant. Part of the project goes through what environmental consultant Kevin Griggs calls “marginally suitable habitat”…

Read More

Project update for March 30, 2015

Overview for March 23 to March 27 Langman finished tree removals and chipped the trees that were removed. Wood chips were spread as mulch for erosion control on the project. Pre-pipe installation silt fence was installed throughout the project. Langman healed up some soft areas on Naples Avenue that were likely created from the thawing…

Read More

Road construction: South Front Street

As part of work to increase sanitary sewer capacity to the west of Front Street, Front Street will be reduced to two lanes near James Van Allen Elementary School beginning Monday, March 30, 2015. Additionally, the sidewalk along the west side of Front Street will also be closed from Vendello Drive to Abigail Avenue. School…

Read More